Up to 230,000 liters of water tank may store the new storm that the Ministry of Agriculture and Water, is undertaking in the former Wastewater Treatment Station-WWTP Santomera South, with an investment of 224.
121 euros.
This project will be completed during the second half of next February, is the creation of a pumping well and the installation of a chest of deal that will connect the new well with the old tank of the WWTP South-up now disused -, turning it into a tank of storms that may be stored on the first episodes of rain storm, in the end the dirtiest by the overloading of solids and minerals that are often present, such as magnesium and nitrates.
Councilman Land Management, Victor Manuel Cerezo, has advance this project designed by the technicians of the Ministry of Agriculture and Water, "will prevent rain water can reach the Azarbe of Merancho, being stored in the tank storms and then pumped to the Sewage Treatment Station-WWTP North, where they will be properly addressed. "
Cranes, shovels, trucks and a group of six operators working in shifts, morning and afternoon despite bad weather, in order to complete the work of adapting the WWTP former warehouse South accordance with the deadlines set by their own counsel.
Source: Ayuntamiento de Santomera