The City Council, pending further analysis to resume work at school (09/09/2016)

Laboratory technicians Industrial Hygiene ISSL (Institute for Occupational Safety and Health) Santomera have returned today to take new samples in school Our Lady of the Rosary.

Tests have been conducted on the covers A and B pavilions, where yesterday finished cleaning tasks that today also end up in the third building.

Their results will determine whether or not possible to start with the installation of new roofs.

"We hope to have the results by the end of next week, because it is right now when the speed is most needed," maintains the Councillor for Education, Maria Jose Medina.

The City Council already has everything ready to start work immediately placement of new roofs, but it is necessary before the ISSL give its approval.

In this regard it is noted that only one of eighteen tests far exceeded the one thousandth, the limit that determines a libe atmosphere of asbestos.

In the current circumstances, every day counts: a small margin can make the difference between the works whether or not completed before October 3, when the incorporation of students of the institute Poet Julian FP Andúgar is planned.

Not being completed the works on that date, students of Primary Our Lady of the Rosary, which started in the course of that school classrooms should be re-housed in prefabricated classrooms.

Source: Ayuntamiento de Santomera

Notice
UNE-EN ISO 9001:2000 - ER-0131/2006 Región de Murcia
© 2024 Alamo Networks S.L. - C/Alamo 8, 30850 Totana (Murcia) Privacy policy - Legal notice - Cookies
Este sitio web utiliza cookies para facilitar y mejorar la navegación. Si continúas navegando, consideramos que aceptas su uso. Más información